In a tenant-to-tenant migration, the order in which workloads move decides how much disruption people feel. Move them in the wrong order and users end up with mail in one tenant, files in another and a Teams client that can't find either.
1. Identities and coexistence
Create or match identities in the target tenant first, and set up coexistence: free/busy, a shared address list and cross-tenant Teams access. From here, people can work together regardless of where their data sits.
2. Pre-stage OneDrive and mail
Copy the bulk of OneDrive and mailbox data in advance, while people keep working in the source tenant. Pre-staging keeps the cutover itself short, because only recent changes need to move on the day.
3. SharePoint sites
Move team sites before the teams that use them switch over, or at the same time. Map permissions to target identities and redirect users to the new locations.
4. Cutover by wave
For each wave, run a final sync of mail and OneDrive, switch the user to the target tenant, and give them clear instructions for signing in and reconnecting Outlook, OneDrive and Teams. Keep waves aligned to teams that work together.
5. Teams
Move Teams after the people who use them, or in the same wave. Channel files move with their SharePoint sites. Channel conversations and chats need third-party tooling if they must be kept.
6. Devices
Re-enrol devices into the target tenant's Intune as each wave cuts over, or shortly after. Plan for the reset or rejoin time, and have support available.
7. Domains and decommission
Move the domain once the last mailbox using it has moved. Then consolidate licences, archive what must be kept and retire the source tenant once retention obligations are met.
The principle
Keep people working together from the start, move the bulk of data before the day, and move each team together. Almost everything else follows from that.